Lessons Learned — Weybridge School Phasing
James Chen·1 Feb 2026
Lessons Learned — Weybridge School Phasing
Context
Phased summer works to an occupied primary school required careful coordination.
What Went Well
- Early engagement with school leadership
- Phasing plan aligned with term dates
- Contractor pre-start meeting covered safeguarding
What Could Improve
- Allow more float between phases (2 weeks minimum)
- DBS checks for all site personnel should be confirmed 4 weeks before, not 2
- Temporary signage and wayfinding needs its own budget line
Recommendations
- For any education project, start safeguarding planning at Stage 2
- Include phasing as a design risk item from Stage 3