Lessons Learned

Lessons Learned — Weybridge School Phasing

James Chen·1 Feb 2026

Lessons Learned — Weybridge School Phasing

Context

Phased summer works to an occupied primary school required careful coordination.

What Went Well

  • Early engagement with school leadership
  • Phasing plan aligned with term dates
  • Contractor pre-start meeting covered safeguarding

What Could Improve

  • Allow more float between phases (2 weeks minimum)
  • DBS checks for all site personnel should be confirmed 4 weeks before, not 2
  • Temporary signage and wayfinding needs its own budget line

Recommendations

  • For any education project, start safeguarding planning at Stage 2
  • Include phasing as a design risk item from Stage 3