Projects/Weybridge School Refurb

Contract Administration

Weybridge School RefurbSurrey County Council

Contract Summary

Procurement

traditional

Contract Form

JCT MW

Administrator

Contract Administrator — Studio Mitchell Architects

Notes

Minor works contract. Single-stage tender completed.

Key Dates

possession

7 May 2026

practical completion

21 Jul 2026

defects end

21 Jul 2027

3

Total Events

3

Open

0

Overdue

Contract Events

issuedEOT-001Extension of Time

EOT claim — asbestos discovery delay

Contractor claims 2-week extension due to unforeseen asbestos.

Issued: 5 Jun 2026Response due: 18 Jun 2026By: James Chen
issuedAI-001Architect Instruction

Asbestos removal — revised specification

Instruction to contractor to proceed with licensed asbestos removal in ceiling void.

Issued: 4 Jun 2026Response due: 11 Jun 2026By: James Chen
draftAI-002Architect Instruction

Acoustic ceiling treatment to main hall

Instruction to include acoustic treatment per change request.

Issued: 2 Jun 2026Response due: 16 Jun 2026By: James Chen