Projects/Weybridge School Refurb

Project Health

Weybridge School Refurb

Health Score

75

On track

Forecast Margin

11.0%

Burn Ratio

1.05x

Alerts

📉

Forecast margin below 5%

critical

Current forecast margin is 8% but trending down. Technical coordination overruns have consumed contingency. Risk of fee loss if trend continues.

5 Mar 2026
🚨

Stage 4 technical design 22% over budget

critical

Stage 4 hours have exceeded budget by 22%. Multiple coordination issues with structural engineer and M&E consultant.

1 Mar 2026

Project approaching loss-making territory

critical

If current burn rate continues, project will become loss-making within 4 weeks. Immediate intervention required.

28 Feb 2026

Burn vs Budget

StageBudgetedActualBurn RatioVarianceProgress
015h14h0.93x-6.7%
130h28h0.93x-6.7%
260h62h1.03x+3.3%
3100h115h1.15x+15.0%
4200h244h1.22x+22.0%

Stage Completion

Preparation

100.0%

Concept

100.0%

Developed Design

100.0%

Technical Design

100.0%

Manufacturing & Construction

0.0%

Health Trend

DateScoreMarginBurn RatioFlags
30 Nov 2024728.0%1.08x
Near LossQuote Review
31 Dec 2024705.0%1.15x
Near LossQuote Review
31 Jan 2025682.0%1.22x
Near LossBilling RiskQuote Review
28 Feb 2025728.0%1.10x
Near LossQuote Review
31 Mar 20257511.0%1.05x

Commercial Summary

Agreed Fee

£72,000

Invoiced

£65,000

Paid

£58,000

WIP

£4,200

Expenses

£2,800

Margin %

12.0%